September 30th 2016

Redevelopment Update - major Summer works at Blackheath High

Vanbrugh Park Redevelopment Phase 2

The redevelopment of the Senior School site started on the 11th July 2016. Rooff, the main contractor, set up site and began works on the complicated business of the re-distribution of services prior to the demolition works. Below is a picture taken on the 23rd September 2016 of the demolition site - the East block has all but gone.

Reconfiguration of SIBCAS Unit

During the holiday the SIBCAS unit was re-configured to accommodate the Science, DT, Art and Music departments as well as a staff work room and the Marketing and Admissions office. 


Junior School

The Nursery Ramp

The Nursery ramp is now complete and ready for use. The workmanship was of a high standard and we are very pleased with the outcome.

Paragon Place

The school managed to negotiate some additional funding to carry out some landscaping works to the Paragon Place entrance. Although further work will be required to complete the entire area, the works that have been undertaken are a vast improvement both aesthetically and in terms of Health and Safety.